Contract Agreement Amount

Rs. 24,42,663

Physical Progress

81.00%

Financial Progress

81.61%

Remaining Payment

Rs. 18

Blacktopped Road Construction Works including Drainage Structures along Pusplal Chowk Gachhiya Sadak Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 076-77

81.00%

Contract Date: 20-Nov-19

Start Date: 20-Nov-19

Completion Date: 14-Mar-2022 (EOT Done)

Project Description

No description available.