Contract Agreement Amount
Rs. 48,83,88,132
Physical Progress
71.00%
Financial Progress
81.49%
Remaining Payment
Rs. 18
Roadway Excavation & Improvement upto Black top Standard along Bahunepati-Dolalghat sector (ch14+500-31+030) Sindhupalchok District
Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)
Fiscal Year: 073-74
Contract Date: 30-May-17
Start Date: 30-May-17
Completion Date: 15-Jul-2023 (EOT Done)
Project Description
No description available.