Contract Agreement Amount
Rs. 20,96,17,123
Physical Progress
80.00%
Financial Progress
81.43%
Remaining Payment
Rs. 18
Design & Build of Sunkoshi River Bridge, Shankarkhola Doban, Rampur-1, Ramechhap
Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)
Fiscal Year: 073-74
Contract Date: 23-Jun-17
Start Date: 23-Jun-17
Completion Date: 04-Jul-2023 (EOT Done)
Project Description
No description available.