Contract Agreement Amount
Rs. 2,11,58,450
Physical Progress
83.00%
Financial Progress
81.35%
Remaining Payment
Rs. 18
Roadway Excavation and Structural works along Diktel-Solu-Junbesi-Khahare-Jiri Bazzar-Tamakoshi-charikot-Khadichaur
Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)
Fiscal Year: 079-80
Contract Date: 13-Dec-22
Start Date: 13-Dec-22
Completion Date: 13-Dec-2023 (EOT Not Done)
Project Description
No description available.