Contract Agreement Amount

Rs. 2,11,58,450

Physical Progress

83.00%

Financial Progress

81.35%

Remaining Payment

Rs. 18

Roadway Excavation and Structural works along Diktel-Solu-Junbesi-Khahare-Jiri Bazzar-Tamakoshi-charikot-Khadichaur

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 079-80

83.00%

Contract Date: 13-Dec-22

Start Date: 13-Dec-22

Completion Date: 13-Dec-2023 (EOT Not Done)

Project Description

No description available.