Contract Agreement Amount
Rs. 2,53,08,607
Physical Progress
0.00%
Financial Progress
80.71%
Remaining Payment
Rs. 19
Construction of RCC Bridge for Pump Canal, Saptari along Rajbiraj Balan Hulaki Road
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, सुनसरी (64)
Fiscal Year: 071-72
Contract Date: 10-Jul-15
Start Date: 10-Jul-15
Completion Date: 26-Oct-2024 (EOT Done)
Project Description
No description available.