Contract Agreement Amount
Rs. 2,39,71,467
Physical Progress
0.00%
Financial Progress
80.70%
Remaining Payment
Rs. 19
Construction of RCC Bridge Kaule Khola Nuwakot
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 073-74
Contract Date: 10-Apr-17
Start Date: 10-Apr-17
Completion Date: 04-Jul-2018 (EOT Not Done)
Project Description
No description available.