Contract Agreement Amount

Rs. 87,05,675

Physical Progress

0.00%

Financial Progress

80.56%

Remaining Payment

Rs. 19

Structural Works on Koshi Highway (Trisule to Nunthala Section)

Office: डिभिजन सडक कार्यालय, धनकुटा (15)

Fiscal Year: 077-78

0.00%

Contract Date: 18-Mar-21

Start Date: 18-Mar-21

Completion Date: 31-Dec-2021 (EOT Done)

Project Description

No description available.