Contract Agreement Amount

Rs. 35,69,950

Physical Progress

0.00%

Financial Progress

80.38%

Remaining Payment

Rs. 19

Construction of Rigid Pavement Works on Gaur Pipara Madhopur Binagra Sundarpur Haraiya Santpur Sadak, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 077-78

0.00%

Contract Date: 9-Jun-21

Start Date: 9-Jun-21

Completion Date: 04-Jul-2021 (EOT Not Done)

Project Description

No description available.