Contract Agreement Amount
Rs. 3,21,09,874
Physical Progress
80.00%
Financial Progress
79.58%
Remaining Payment
Rs. 20
Extension & Improvement of Dewariya Behadababa Road, Kailali
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 071-72
Contract Date: 15-Jul-15
Start Date: 15-Jul-15
Completion Date: 16-Oct-2020 (EOT Done)
Project Description
No description available.