Contract Agreement Amount
Rs. 1,73,30,609
Physical Progress
0.00%
Financial Progress
79.40%
Remaining Payment
Rs. 20
Road Upgrading works on Road inside permimeter of Birendra Peace work training center Panchkhal, Kavre
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 075-76
Contract Date: 3-Jun-19
Start Date: 3-Jun-19
Completion Date: 16-Nov-2019 (EOT Not Done)
Project Description
No description available.