Contract Agreement Amount
Rs. 8,96,55,647
Physical Progress
95.00%
Financial Progress
79.18%
Remaining Payment
Rs. 20
Construction of RCC Bridge over Chaudhar Nadi,Bedkot Na.Pa. 5&6, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 21-May-17
Start Date: 21-May-17
Completion Date: 30-Jul-2021 (EOT Done)
Project Description
No description available.