Contract Agreement Amount

Rs. 1,00,29,825

Physical Progress

80.00%

Financial Progress

79.16%

Remaining Payment

Rs. 20

Roadway Improvement work along Rakam-pilka-Deuli-kafalkot-khaneta-sima-Thala-Raikar-Jajarkot sadak

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

80.00%

Contract Date: 15-Jun-20

Start Date: 15-Jun-20

Completion Date: 13-Feb-2021 (EOT Not Done)

Project Description

No description available.