Contract Agreement Amount
Rs. 4,45,39,747
Physical Progress
0.00%
Financial Progress
78.87%
Remaining Payment
Rs. 21
Construction of RCC Bridge over Koya Khola at Terhathum District.
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 071-72
Contract Date: 9-Jun-15
Start Date: 9-Jun-15
Completion Date: 26-Nov-2019 (EOT Done)
Project Description
No description available.