Contract Agreement Amount
Rs. 7,20,98,192
Physical Progress
0.00%
Financial Progress
78.40%
Remaining Payment
Rs. 21
Roadway Excavation, Cross & Side Drain, Structure and Gravelling Works on Belbas - Nuwakot - Dovan Road, Palpa Sector [CH: 10+500 Km to CH: 17+650 Km], Palpa
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 072-73
Contract Date: 13-Jul-16
Start Date: 28-Jul-16
Completion Date: 28-Jul-2017 (EOT Not Done)
Project Description
No description available.