Contract Agreement Amount
Rs. 1,57,76,629
Physical Progress
94.44%
Financial Progress
78.39%
Remaining Payment
Rs. 21
Construction of RCC T-Beam Bridge over Surkada River at Mahakali Highway, Darchula in Surkada Khola, Mahakali Highway (Ch. 303+918), Dhap, Darchula
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 072-73
Contract Date: 12-Feb-16
Start Date: 26-Feb-16
Completion Date: 12-Apr-2020 (EOT Done)
Project Description
No description available.