Contract Agreement Amount

Rs. 3,93,82,088

Physical Progress

78.00%

Financial Progress

78.31%

Remaining Payment

Rs. 21

Road Improvement and Rehabilitation works on Koshi Highway (Hile-Basantapur-Deurali ) and Basantapur-Myaglung road

Office: डिभिजन सडक कार्यालय, धनकुटा (15)

Fiscal Year: 072-73

78.00%

Contract Date: 5-Jul-16

Start Date: 5-Jul-16

Completion Date: 15-Dec-2017 (EOT Done)

Project Description

No description available.