Contract Agreement Amount

Rs. 15,23,073

Physical Progress

80.00%

Financial Progress

78.00%

Remaining Payment

Rs. 22

Road Improvement works of Budhabagar - Babla-Khaptad Road Section, Achham

Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)

Fiscal Year: 077-78

80.00%

Contract Date: 19-Feb-21

Start Date: 19-Feb-21

Completion Date: 13-Jun-2021 (EOT Not Done)

Project Description

No description available.