Contract Agreement Amount

Rs. 3,08,70,782

Physical Progress

77.94%

Financial Progress

77.93%

Remaining Payment

Rs. 22

Roadway Improvement works at Chainage 38+700 to 53+000 along Surkhet-Jumla Road, Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

77.94%

Contract Date: 11-Apr-21

Start Date: 12-Apr-21

Completion Date: 14-Jul-2021 (EOT Not Done)

Project Description

No description available.