Contract Agreement Amount
Rs. 2,31,93,345
Physical Progress
0.00%
Financial Progress
77.77%
Remaining Payment
Rs. 22
Construction of RCC Girder Bridge with Pile Foundation Over Kath River along Simra Kolvi Road,Bara
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 070-71
Contract Date: 8-Jul-14
Start Date: 8-Jul-14
Completion Date: 07-Jul-2016 (EOT Not Done)