Contract Agreement Amount
Rs. 17,22,000
Physical Progress
70.00%
Financial Progress
77.67%
Remaining Payment
Rs. 22
Reactive Maintenance Works along Rapti Highway (Ramri - Shitalpati ) in Salyan district.
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 078-79
Contract Date: 8-Sep-21
Start Date: 15-Sep-21
Completion Date: 14-Dec-2022 (EOT Done)
Project Description
No description available.