Contract Agreement Amount

Rs. 1,61,22,880

Physical Progress

77.00%

Financial Progress

77.51%

Remaining Payment

Rs. 22

Pavement work Including Cross drainage and retaining Structures along Ramdhuni Baithar Kutipul Barahachetra Aaitabare Chakraghati Sadak, Sunsari

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

77.00%

Contract Date: 3-Feb-22

Start Date: 3-Feb-22

Completion Date: 11-Jun-2023 (EOT Done)

Project Description

No description available.