Contract Agreement Amount
Rs. 18,82,847
Physical Progress
80.00%
Financial Progress
77.04%
Remaining Payment
Rs. 22
Construction of Drain Works at Sirsiya Hajminiya Pathara Sadak, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 077-78
Contract Date: 20-Dec-20
Start Date: 28-Dec-20
Completion Date: 17-Apr-2021 (EOT Not Done)
Project Description
No description available.