Contract Agreement Amount

Rs. 64,72,486

Physical Progress

80.00%

Financial Progress

76.65%

Remaining Payment

Rs. 23

Corridor - Dhurpur-Kholete to Talkuna Sadak,Baglung

Office: Road Division, Baglung (254)

Fiscal Year: 076-77

80.00%

Contract Date: 24-Feb-20

Start Date: 24-Feb-20

Completion Date: 09-Jul-2020 (EOT Not Done)

Project Description

No description available.