Contract Agreement Amount
Rs. 7,00,53,915
Physical Progress
99.94%
Financial Progress
76.51%
Remaining Payment
Rs. 23
Periodic Maintenance Works along Ganaha-Chackchake-Liwang-Madichaur-Darbot (NH53)(Sulichaur-Liwang-Madichaur Section )Road in Rolpa District
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 078-79
Contract Date: 6-Sep-22
Start Date: 6-Sep-22
Completion Date: 06-Sep-2023 (EOT Not Done)
Project Description
No description available.