Contract Agreement Amount

Rs. 61,51,14,606

Physical Progress

80.00%

Financial Progress

76.08%

Remaining Payment

Rs. 23

Upgrading of Kalyankot Gobardiha Gadhawa Rajpur Road (Ch. 46+840-Ch.66+840)

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वाके (98)

Fiscal Year: 075-76

80.00%

Contract Date: 17-Nov-19

Start Date: 2-Dec-19

Completion Date: 17-Oct-2023 (EOT Done)

Project Description

No description available.