Contract Agreement Amount
Rs. 4,70,96,171
Physical Progress
68.00%
Financial Progress
75.90%
Remaining Payment
Rs. 24
Construction of Two-webbed Pre-stressed RCC Kamal Khola Bridge (Pile Foundation) at Baigundhara Panchgachhi Road, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 075-76
Contract Date: 25-Jul-19
Start Date: 25-Jul-19
Completion Date: 23-Jul-2021 (EOT Not Done)
Project Description
No description available.