Contract Agreement Amount

Rs. 19,40,15,626

Physical Progress

78.00%

Financial Progress

75.67%

Remaining Payment

Rs. 24

Construction of Additional Spans and River training works at Ratuwa Bridge,Postal Highway (Jhapa/Morang)

Office: योजना तथा अनुगमन महाशाखा (HMIS तथा ICT शाखा) (6)

Fiscal Year: 079-80

78.00%

Contract Date: 2-Jan-23

Start Date: 2-Jan-23

Completion Date: 02-Jul-2025 (EOT Not Done)

Project Description

No description available.