Contract Agreement Amount

Rs. 37,55,43,474

Physical Progress

0.00%

Financial Progress

75.23%

Remaining Payment

Rs. 24

MIDHLDNG3371384/073/074

Office: Puspalal (Midhill) Road Project, Dailekh (277)

Fiscal Year: 073-74

0.00%

Contract Date: 31-May-17

Start Date: 31-May-17

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.