Contract Agreement Amount
Rs. 73,98,405
Physical Progress
80.00%
Financial Progress
75.12%
Remaining Payment
Rs. 24
Road Widening and upgrading works on ARM service track
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 21-Dec-20
Start Date: 21-Dec-20
Completion Date: 05-Jun-2021 (EOT Not Done)
Project Description
No description available.