Contract Agreement Amount
Rs. 92,31,012
Physical Progress
67.41%
Financial Progress
74.85%
Remaining Payment
Rs. 25
Road Maintenance in Anarkholi-Khodpe-Patan Section of Pushpalal (Mid Hill) Highway (NH03)
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 077-78
Contract Date: 14-Mar-21
Start Date: 14-Mar-21
Completion Date: 03-Jun-2021 (EOT Not Done)
Project Description
No description available.