Contract Agreement Amount
Rs. 2,94,15,537
Physical Progress
75.00%
Financial Progress
74.82%
Remaining Payment
Rs. 25
Construction of a Simply Supported RCC Bridge (1*24=24) Over Suni Khola along Mohanapul-Attariya Road, Kailali
Office: Unknown (1)
Fiscal Year: 077-78
Contract Date: 8-Feb-21
Start Date: 8-Feb-21
Completion Date: 24-Jun-2024 (EOT Done)
Project Description
No description available.