Contract Agreement Amount

Rs. 3,02,63,746

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Highway Upgrading & Rehabilitation Works Along Shitalpati Salyan Kupinde Baluwasangrahai Road (Ch 9+000 to 20+000) in Salyan District.

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 080-81

0.00%

Contract Date: 3-Nov-23

Start Date: 3-Nov-23

Completion Date: 31-Jul-2024 (EOT Not Done)

Project Description

No description available.