Contract Agreement Amount
Rs. 34,67,33,929
Physical Progress
75.28%
Financial Progress
74.78%
Remaining Payment
Rs. 25
Blacktop and roadway improvement works, Tehrathum District. Chainage : (Km : 83+000 to 93+000)
Office: Puspalal (Midhill) Road Project, Panchthar (273)
Fiscal Year: 071-72
Contract Date: 17-Sep-15
Start Date: 17-Sep-15
Completion Date: 15-Jul-2023 (EOT Done)
Project Description
No description available.