Contract Agreement Amount

Rs. 3,57,90,025

Physical Progress

73.76%

Financial Progress

73.76%

Remaining Payment

Rs. 26

Construction RCC Bridge at Govindapur on Katnu Khola to Tribhuvan chowk Road,Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 071-72

73.76%

Contract Date: 6-Oct-15

Start Date: 6-Oct-15

Completion Date: 07-Jul-2020 (EOT Done)

Project Description

No description available.