Contract Agreement Amount
Rs. 2,83,24,629
Physical Progress
15.00%
Financial Progress
73.55%
Remaining Payment
Rs. 26
Upgrading works on Panauti namobuddhaSection of Lakuribhanjyang-Panauti-Namobuddha Road
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 071-72
Contract Date: 6-May-15
Start Date: 6-May-15
Completion Date: 13-Apr-2018 (EOT Done)