Contract Agreement Amount

Rs. 45,88,678

Physical Progress

0.00%

Financial Progress

73.51%

Remaining Payment

Rs. 26

Construction of blacktop & Rcc Box culvert along Ramaulitole Bateshwar Bazar( Nala Kalopatre) ,Dhanusha

Office: डिभिजन सडक कार्यालय, धनुषा (17)

Fiscal Year: 076-77

0.00%

Contract Date: 8-Dec-19

Start Date: 8-Dec-19

Completion Date: 11-Oct-2021 (EOT Done)

Project Description

No description available.