Contract Agreement Amount

Rs. 7,45,14,112

Physical Progress

98.00%

Financial Progress

72.87%

Remaining Payment

Rs. 27

Construction of Bridge over Mohana River in Between Raikuwar bichawa-08 Kanchanpur & Dhangadhi Municipility-02, Kailali

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 070-71

98.00%

Contract Date: 15-Jul-14

Start Date: 5-Jul-14

Completion Date: 14-Jan-2022 (EOT Done)

Project Description

No description available.