Contract Agreement Amount

Rs. 17,66,94,334

Physical Progress

0.00%

Financial Progress

72.49%

Remaining Payment

Rs. 27

Road Works along Tulsipur-Purandhara-Botechaur Road in Dang and Salyan District

Office: सडक डिभिजन, दाङ्ग (31)

Fiscal Year: 073-74

0.00%

Contract Date: 15-Jun-17

Start Date: 15-Jun-17

Completion Date: 17-Jun-2020 (EOT Not Done)

Project Description

No description available.