Contract Agreement Amount
Rs. 17,66,94,334
Physical Progress
0.00%
Financial Progress
72.49%
Remaining Payment
Rs. 27
Road Works along Tulsipur-Purandhara-Botechaur Road in Dang and Salyan District
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 073-74
Contract Date: 15-Jun-17
Start Date: 15-Jun-17
Completion Date: 17-Jun-2020 (EOT Not Done)
Project Description
No description available.