Contract Agreement Amount
Rs. 82,86,320
Physical Progress
100.00%
Financial Progress
72.47%
Remaining Payment
Rs. 27
Improvement of Tallo Garjamini -Asaina- Sikalpatti - Thada -Janapuri -Dhakaniya- Ranipur- Basantapur- Bansaha - Ganeshpur -Deepnagar -Amarpur- Naukhari -Manikapur dham road, Kanchanpur (Naukhuri To Manikapur, Chainage-2+100 to 4+000)
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 076-77
Contract Date: 23-Jun-20
Start Date: 30-Jun-20
Completion Date: 28-Mar-2021 (EOT Not Done)
Project Description
No description available.