Contract Agreement Amount

Rs. 2,63,91,782

Physical Progress

100.00%

Financial Progress

72.34%

Remaining Payment

Rs. 27

Construction of RCC Bridge over Bhasi Khola, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 073-74

100.00%

Contract Date: 20-Jul-17

Start Date: 20-Jul-17

Completion Date: 15-Oct-2020 (EOT Done)

Project Description

No description available.