Contract Agreement Amount
Rs. 59,29,772
Physical Progress
0.00%
Financial Progress
71.78%
Remaining Payment
Rs. 28
Construction Of RCC Slab Culvert at Motipur Ch 45+100 along Ghorahi Tulsipur Road in Dang District
Office: सडक डिभिजन, दाङ्ग (31)
Fiscal Year: 075-76
Contract Date: 27-Nov-18
Start Date: 27-Nov-18
Completion Date: 25-May-2019 (EOT Not Done)
Project Description
No description available.