Contract Agreement Amount

Rs. 3,31,82,778

Physical Progress

0.00%

Financial Progress

71.56%

Remaining Payment

Rs. 28

Construction of RCC Bridge Over Jiri Khola, Dolakha

Office: डिभिजन सडक कार्यालय, दोलखा (18)

Fiscal Year: 073-74

0.00%

Contract Date: 20-Apr-17

Start Date: 20-Apr-17

Completion Date: 30-Jul-2019 (EOT Done)

Project Description