Contract Agreement Amount
Rs. 1,60,45,931
Physical Progress
0.00%
Financial Progress
71.55%
Remaining Payment
Rs. 28
सगरमाथा राजमार्गको मिर्चैया कटारी खण्ड (H09), सिराहा
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 073-74
Contract Date: 1-Feb-17
Start Date: 1-Feb-17
Completion Date: 07-Jul-2017 (EOT Not Done)