Contract Agreement Amount

Rs. 1,41,20,782

Physical Progress

72.00%

Financial Progress

71.47%

Remaining Payment

Rs. 28

Road Impovement work with Drainage, Humepipe culvert along Laundihawa Jogada Masina Mohsar Bharat sima Rupandehi (Chainage from Sukrauli to Bhabhani sector Election area no.4 )

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 076-77

72.00%

Contract Date: 18-Jun-20

Start Date: 18-Jun-20

Completion Date: 13-Apr-2023 (EOT Done)