Contract Agreement Amount

Rs. 1,16,81,379

Physical Progress

68.15%

Financial Progress

71.33%

Remaining Payment

Rs. 28

Road Upgrading and Rehabilitation Works along Ganaha Khola- Chakchake Road Section ( Ch 8+000 to 43+000) NH53-002, NH09-027 and Chakchake Madichaur DB Section (Ch 0+000 to 15+000) NH53-003, Pyuthan District

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 079-80

68.15%

Contract Date: 10-May-23

Start Date: 10-May-23

Completion Date: 10-May-2023 (EOT Not Done)

Project Description

No description available.