Contract Agreement Amount
Rs. 2,77,53,689
Physical Progress
71.00%
Financial Progress
71.02%
Remaining Payment
Rs. 28
Construction of RCC Bridge (20m Span) over Sireni khola Bridge,Bheriganga-5 Surkhet(CN:RDSKT/33701122-4/078/79-54)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 078-79
Contract Date: 13-Mar-22
Start Date: 20-Mar-22
Completion Date: 12-Jun-2023 (EOT Not Done)
Project Description
No description available.