Contract Agreement Amount

Rs. 15,89,42,185

Physical Progress

75.00%

Financial Progress

71.00%

Remaining Payment

Rs. 29

Piloting of Multi-Year Road Maintenance of East- West Highway (Karnali to Attariya Section, Km 901+000 - Km 980+000)

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 075-76

75.00%

Contract Date: 19-Feb-19

Start Date: 19-Feb-19

Completion Date: 18-Feb-2022 (EOT Done)