Contract Agreement Amount
Rs. 3,94,35,410
Physical Progress
2.60%
Financial Progress
70.39%
Remaining Payment
Rs. 29
Upgrading and Rehabiliation of Road in Gokuleshwar - Khalanga Section of Satbanjh-Gokuleshwar-Tinkar Highway NH-66 , CH 54+000 - 126+000
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 079-80
Contract Date: 9-Dec-22
Start Date: 9-Dec-22
Completion Date: 05-Jul-2023 (EOT Not Done)
Project Description
No description available.