Contract Agreement Amount
Rs. 1,46,33,018
Physical Progress
100.00%
Financial Progress
70.15%
Remaining Payment
Rs. 29
oad Upgrading Work on Koshi Highway (Hile to Basantpur Section)
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 078-79
Contract Date: 27-Mar-22
Start Date: 27-Mar-22
Completion Date: 29-Jun-2022 (EOT Not Done)
Project Description
No description available.