Contract Agreement Amount
Rs. 55,70,158
Physical Progress
70.00%
Financial Progress
70.08%
Remaining Payment
Rs. 29
Construction of Dakshin simawarti kshetrako aadharbhut bikaslai prathamiktama rakher dakshin-uttar link purwadhaar nirman (Bhagwanpur Border-Dhakdahi-Ramnagar-Sikathanchok-Dhekabar-Khaireni Road)
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 25-Nov-19
Start Date: 25-Nov-19
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.